A state-owned lab near Orangeville where Valar Atomics' DOE-authorized test reactor reached criticality in June 2026. The rents, the county land sale, the Inland Port link, and the state permit we could not find.
General location only, near Orangeville in Emery County. Not a parcel boundary.
H.B. 410 (2024) created the San Rafael Energy Lab and an Energy Research Fund with $2 million one-time. Utah News Dispatch reported the plan as the state buying the lab from Emery County, with $1 million more for operations through 2025. The Office of Energy Development runs the lab fund. Dr. Jaron Wallace directs the lab.
The Utah Energy Research Board's Nov. 12, 2025 minutes list the tenants' monthly rents "per the finance overview": Valar Atomics, three-year lease, $29,000 a month; Natura Resources, leasing "both labs," $71,000 a month; and NuCube, with an agreement and grant applications. The same minutes record a $2.2 million appropriation for the state's advanced nuclear institute and a $6.5 million used-fuel recycling grant application with Curio. Board member Mason Baker asked whether the "Greenfield State" standard used for Valar would apply to any private party; the answer recorded is that "it's an ongoing discussion."
Checked on the rendered PDF, page 3: "Rentals: $29,000 - Valar $71,000 - Natura - Monthly payments for rental." Page 4: "The Institute received $2.2 Million in appropriations this year."
H.B. 78 (2026) exempts interim storage of waste from a DOE-authorized test reactor at a state-owned facility from Utah's high-level waste law, but only if the project "is permitted and licensed by the division" (Utah Code 19-3-321).
DOE's form says spent fuel goes to dry storage for shipment to a DOE-approved facility, and low-level waste is under 1 cubic meter a year. Whether a state permit exists that would meet 19-3-321 is an open question, not a finding.
Emery County's agendas show it moving to sell parcel 04-0019-0030, next to the lab, to Valar. The steps: a staging-area letter and the start of the sale (Mar. 17, 2026), a public hearing (Apr. 7), a purchase agreement with the county's Local Building Authority plus annexation into Orangeville (May 19), and a due-diligence extension (July 7). A local news headline (ETV News, May 28) said the commission "OKs Land Sale to Valar Atomics."
| Date | Body | What happened |
|---|---|---|
| June 3, 2025 | Emery County Commission | Commissioner Jordan Leonard said the commission wanted community input first and would "aggressively" pursue nuclear if residents supported it. |
| June 17, 2025 | Emery County Commissioners | Public input hearing on nuclear industries. No vote. Speakers for and against (see below). Minutes are a Word file we could not open; account from Castle Country Radio. |
| July 8, 2025 | Public meeting | Valar town hall; Valar called it a $50 million project with a 41,560 sq. ft. building. |
| Sept. 11, 2025 | — | Valar groundbreaking. |
| Nov. 12, 2025 | Utah Energy Research Board | Minutes list lab rents: Valar, three-year lease, $29,000 a month; Natura Resources, $71,000 a month. |
| Feb. 17, 2026 | Emery County Commission | Voted 3-0 to draft a letter of support for Valar; legal counsel to approve it. Valar's Max Ukropina: "We've been working on this project in secret for about seven months." Signed letter not found. |
| Mar. 17, 2026 | Emery County Commission | Agenda: let Valar use parcel 04-0019-0030 as a staging area; start the sale of that parcel to Valar, subject to a hearing and two appraisals. |
| Apr. 7, 2026 | Emery County Commission | Public hearing on selling parcel 04-0019-0030 to Valar; price to be the average of two appraisals. |
| May 19, 2026 | Emery County Commission | Agenda: purchase and sale agreement among the county, its Local Building Authority and Valar; notices to annex the parcel into Orangeville; a resolution to remove it from the Inland Port's Castle Country project area. Price, acreage and vote not found. |
| June 18, 2026 | DOE / Valar | Ward 250 reaches criticality. |
| July 7, 2026 | Emery County Commission | Ratified a 30-day extension of the due-diligence period in the Valar purchase agreement. |
According to Castle Country Radio: Commissioner Keven Jensen opened. Ron Dunn, a staffer for Rep. Mike Kennedy, spoke for. Kevin Butler called himself "pro-nuclear, and... pro-coal" and asked for more transparency. Lab director Jaron Wallace said the lab shares information unless it is under a nondisclosure agreement. Susan Sitterud and Barbra Jones, an atomic-testing cancer survivor, spoke against. Sheriff Tyson Huntington spoke on security.
Emery County posts its minutes as Word files, which we could not open. Those minutes are unread, not empty. Audio recordings are posted on the Utah Public Notice Website.
DOE's approval has no separate emergency-planning section. Valar told the Castle Dale council (Mar. 12, 2026) it had coordinated with local emergency management and posted a job for a "Head of Utah Site, Emergency Management and Security." No county emergency plan was found.
How we read these records: most documents were read as text through a reading tool on Oct. 29, 2026, not as rendered pages. Short quotes are marked; check any quote against the original before reusing it. "Not found in the records searched" means we looked and did not find it, not that it does not exist.
Utah Hive Politicsfrom the publisher of The Weber County HiveIndependent · Accountability · JournalismThe Weber County Hive and Utah Hive Politics: the people's publication. We investigate what's best for the public as a whole, not for any party or special interest group. We report public records. You decide.
Send a tipTips we checkedSee a mistake? Tell us
We never name tipsters. When we correct a page, the fix and its date are shown on the page.
Nuclear Energy shelf · Master Index (Hive library) · Read on Substack