Case file · Carbon County · NE 300.02

Carbon County: the Wellington Lease

The state trust land board voted unanimously to approve a lease agreement with Valar Atomics for 640 acres north of Wellington. Every public speaker who addressed it was in favor. Here are the terms.

Posted Oct. 29, 2026 · Updated Oct. 29, 2026

The short version

WHERE
Carbon County · state trust land north of Wellington (SULA 2095) · federal land near Price
WHO
640
acres in the lease agreement approved for Valar north of Wellington (480 now; 160 more if the Guard moves)
~9,000
acres of federal land Valar has asked BLM for near Price
All
public speakers who addressed the Valar lease at both board meetings spoke in favor

Where it is

General areas only. The lease is in Section 16, Township 14 South, Range 11 East; the federal request is reported as "near Price."

The Trust Lands vote

Aug. 20, 2026: the Trust Lands Administration board discussed the lease. No motion or vote. Speakers: Carbon County Commissioners Larry Jensen, Tony Martines and Jared Haddock; Jake Garfield, deputy director of the Office of Energy Development, whose office is Valar's landlord at the San Rafael lab; and Jess Housekeeper of Valar. All who addressed the lease spoke in favor (one online speaker, Sean Jordan, did not address Valar). The agency's Advocacy Office director, Liz Mumford, "expressed support." The minutes list trustees John Baza and Mike Mower as absent but also record both asking questions. We report both until the audio settles it.

Sept. 17, 2026: approved. Trustee Mike Mower moved to approve "on the terms set forth in the board memorandum." Chair Mike Nelson announced the vote as unanimous; the transcript does not make clear who seconded, and records no individual votes. Everyone who spoke about the lease was in favor, including Valar's Harry Hansen, Jess Housekeeper, Terry Bell and Ben Orgill, and Cory Gardner (described by East Idaho News as Valar's head of commercial development); Commissioners Jensen, Haddock and Martines (online: "They have nothing to hide"), and Office of Energy Development deputy director Tracy Rees: "I just cannot recommend strongly enough a partnership with Valor" (spelling as in the transcript).

Chair Nelson said: "We weren't always sure what to ask about... this was a new project for us at the trust." Staff said there is no lockout period. Kael Weston, a Federalism Commission member, spoke online about workforce housing, not the lease. The motion approved the agreement on the memo's terms and had staff finalize it; the signed lease was not found posted.

The lease terms

Lease termWhat the board memo says
LandTrust land lease SULA 2095, Township 14 South, Range 11 East, Section 16: 640 acres. 480 acres now; 160 acres used by the Utah National Guard can be added if the Guard moves.
Length50 years plus two 25-year extensions
Signing bonus$400,000
Rent per acre$30 a year in years 1–5; $206.25 in year 6; $418.75 in year 7; $625 in years 8–10; CPI adjustments from year 11
Buyout optionAny time, for the greater of a 50-year payment value or the appraised value. Examples: year 10, $10,164,109; year 20, $12,055,410; year 25, $14,675,590
WaterThe area is "fully appropriated"; Valar must buy existing water rights and file a change application
Nuclear wasteAny part used for radioactive waste storage must be bought first. Spent-fuel storage on trust land is not allowed under the lease
Listed usesGas-cooled reactor power, TRISO fuel making, hydrogen and synthetic fuels, "partnering with data centers," desalination, steel, concrete, workforce training
AppraisalNo appraisal of the 640 acres is in the board packet

Federal land and the county

Valar has filed an initial application with the federal Bureau of Land Management for about 9,000 acres near Price ("Project Beehive"). BLM says it is "currently reviewing the application for completeness." If it moves forward, a notice of realty action, an environmental review and public comment would follow. No serial number or filing date was found in a federal record.

How many reactors? NPR reported company documents describing "some 456" reactors and about 9.6 gigawatts. KUTV reported "about 70." Neither number appears in any federal record we found, so we do not treat either as fact.

Oct. 6, 2026, Carbon County Planning Commission: Valar presented; CEO Isaiah Taylor said, "If the community doesn't want us here, we won't do it" (KUTV). No public comment was taken and no action was taken. The same night, a separate gas-powered "Technology Park" permit (Altigen, 1,236 acres east of Wellington) was tabled to Nov. 10.

County Commission agendas for June 17, Sept. 16 and Oct. 7, 2026 showed no Valar, data center or nuclear item. A county statement reported July 3, 2026 said some companies would not explore the county without nondisclosure agreements. Whether the county holds one with Valar was not found.

Where this connects

Questions to ask, and to whom

Sources and how we read them ▾

How we read these records: most documents were read as text through a reading tool on Oct. 29, 2026, not as rendered pages. Short quotes are marked; check any quote against the original before reusing it. "Not found in the records searched" means we looked and did not find it, not that it does not exist.

  1. Trust Lands Administration board: Aug. 20, 2026 minutes 1490469 and transcript 1479057; Sept. 17, 2026 notice 1107027, packet and board memo 1488167, transcript 1492511
  2. NPR/KUER, Sept. 30, 2026; East Idaho News/Utah News Dispatch, Oct. 1, 2026 (BLM application)
  3. KUTV, Oct. 6, 2026; ABC4, Oct. 8, 2026; Carbon County Planning Commission notice 1110647 (audio 1498213.MP3)
  4. Carbon County Commission notices 1089483, 1107635, 1112913; county statement as reported by Grist/Canary Media, Oct. 14, 2026
Utah Hive Politicsfrom the publisher of The Weber County HiveIndependent · Accountability · Journalism

The Weber County Hive and Utah Hive Politics: the people's publication. We investigate what's best for the public as a whole, not for any party or special interest group. We report public records. You decide.

Send a tipTips we checkedSee a mistake? Tell us

We never name tipsters. When we correct a page, the fix and its date are shown on the page.

Nuclear Energy shelf · Master Index (Hive library) · Read on Substack