Data Centers · Case File · Statewide · Power Series 3 of 3
It's Happening Statewide: Utah's Data Centers and Their Own Power Plants
Two-thirds of the data center capacity under construction in Utah is planned to run behind the meter or off the public grid. Region by region, the same three pieces keep showing up: local zoning, a 2025 state law, and nuclear as the long-term power source.
The Weber County Hive — We report public records. You decide.
48
data centers operating in Utah, about 920 MW
2,600 MW
more under construction in seven projects
1,700 MW
of that planned behind the meter or off the grid, about two-thirds
2031
year federal reliability regulators project elevated grid risk for Utah
The short version
Utah's biggest new data centers are being built with their own power plants, mostly natural gas for now.
A 2025 law, S.B. 132, lets any customer using 100 megawatts or more do that when Rocky Mountain Power can't serve it in time or on agreed terms.
Nuclear is offered as the long-term source in several regions, and in the documented cases it is tied to specific campuses.
The law keeps those costs off other customers' bills. It also means other customers don't receive that power.
Words to know
Tap or click a card to flip it.
The numbers
Source: Kem C. Gardner Policy Institute, "Data Center Growth in Utah and the United States," April 2026. The grid figure is the remainder of 2,600 minus 1,700, rounded.
Where Utah's data centers are today: 48 operating, about 920 MW. The ten largest make up nearly 80% of that.
Under construction: seven projects, about 2,600 MW. Joule's campus near Delta is the biggest at 1,400 MW for its current phase.
Grid warning: the fact sheet says the North American Electric Reliability Corporation projects elevated grid risk for Utah in 2031, when supply may fall short under extreme conditions.
Proposed, at full planned size: the Salt Lake Tribune's September map lists about 65 sites, with campuses in Box Elder, Millard, Duchesne, Iron, Carbon and Utah counties listed at a gigawatt or more.
The same three pieces, region after region
flowchart LR
A["1. Local zoning A county, city or MIDA allows the data center or the power plant"] --> B["2. S.B. 132 (2025) 100 MW+ users may get power from their own private plant"]
B --> C["3. The power source Natural gas now. Nuclear offered for later."]
C --> D["Result Costs stay off other bills. Power stays off the grid."]
Pick a region
Region
Biggest data center project(s)
Piece 1: Zoning
Piece 2: Own power
Piece 3: Nuclear tie
Box Elder
Stratos, 7.5 GW proposed
MIDA project area, April 2026
MIDA describes dedicated on-site power
Reactors permitted in draft standards; Brigham City SMR hub nearby
Millard
Creekstone (>10 GW goal), Joule (4 GW)
County rezoned both
Both building their own gas power
Creekstone nuclear study (MOU)
Utah County
Meta, QTS, Tract, Google site
Eagle Mountain zoning; energy overlay zone July 2026
Gas generators approved for three data centers; Meta gas plant filed
City studied small reactors; resident pushback
Tooele
Zenith, 500 MW (paused)
Inland Port project area
UIPA loan listed a power plant among uses
Federal nuclear campus bid
Weber
None proposed
Data centers permitted in M-T zone since 2023
S.B. 132 applies
Nuclear symposium Aug. 2026
Carbon
Valar campus; Altigen "Jurassic Spark"
Trust Lands lease; county pipeline agreement
Altigen: 250 MW gas plant to start
Valar reactor campus
Emery
Valar + Nvidia, 30 MW
State-owned lab
Fully reactor-powered, per the companies
Valar test reactor; Green River revival
Iron, Duchesne
Antelope 1.5 GW, Red Butte 1.5 GW, Nine Mile 1 GW+
Proposed
Not found in records reviewed
None found
On the map
Pins are approximate, placed at the town or valley named in public records. Click a pin for details.
Why the pieces line up: the utility can't keep up
Rocky Mountain Power's only firm reactor plan is TerraPower's plant in Kemmerer, Wyoming, around 2032. Utah would share its roughly 500 MW with other Western states.
Developers say they can't wait. Google delayed an Eagle Mountain campus over power supply. Joule's managing partner told reporters the company is excited about nuclear someday but can't wait for it, so it is building gas power.
S.B. 132 is the path. If the utility can't finish its study or agree on terms in time, a large customer may contract with a private generator. A fully off-grid "closed private generation system" is exempt from regulation as a public utility (§54-26-504).
Who keeps showing up
These are documented roles, listed so readers can see the same names across regions. Holding more than one role is not, by itself, a sign of wrongdoing.
Who
Role in each place
Chris Hayter Hi Tech Solutions; Fulcrum Point Holdings
Brigham City: signed the April 29, 2025 SMR-300 agreement with the state as Hi Tech's president and COO. Green River: his Fulcrum Point formed a joint venture with Blue Castle in May 2026 to revive the Green River plant. Weber County: panelist at the Aug. 5, 2026 nuclear "education" symposium, where he told the crowd Utah leaders are listening to the industry.
Utah Office of Energy Development
Weber County: co-hosted the Aug. 5 symposium; its spokesperson said the goal is to hear residents' fears. Statewide: similar outreach in Carbon, Grand, Summit, Wayne and Duchesne counties. Brigham City: Director Emy Lesofski signed the Holtec agreement. Emery: Lesofski praised Valar at its July 1 event. Carbon: Deputy Director Jake Garfield spoke in favor of the Valar lease at the Aug. 20 Trust Lands meeting.
Sen. Scott Sandall & Rep. Colin Jack
Primary sponsor and House sponsor of S.B. 132 (2025). Sandall said the law lets Rocky Mountain Power serve data centers, AI and large manufacturers without handcuffs.
Read this fairly
Promoting energy development is the Office of Energy Development's job under Operation Gigawatt. The point here is a narrower one for readers: the office that runs the public "education" events is also a partner in specific projects. That's worth knowing when you sit in one of its sessions.
Same areas, already marketed
EDCUtah's Site Ready Utah program markets large sites in the same areas as several of these projects, including a West Weber County Mega Site, a Millard County Mega Site and a Carbon Highway 10 Mega Site. Matching the sites to specific projects would take parcel numbers. EDCUtah case file →
What this page does not say
That anyone coordinated these projects. The record shows the same law, the same state office and some of the same people. It does not show a plan.
That every proposed data center will be built. Several are proposals only; Tooele's is paused.
That nuclear will be built at any data center. In Utah, so far, only a test reactor is operating.
The other side
Ratepayers are protected from these costs. S.B. 132 requires large users to pay all their own costs. Michele Beck of Utah's Office of Consumer Services called it one of the best ideas out there for protecting customers.
Off-grid plants don't compete for grid power. A campus making its own power isn't drawing on supply that homes and businesses use.
Rural counties want the tax base. Millard and Carbon officials point to lost coal jobs and new tax revenue. Carbon County coal mines have produced none since 2023.
The policy is public. Operation Gigawatt's goal of doubling power production is stated openly by the governor.
Questions to ask, and whom to ask
Utah Public Service Commission
S.B. 132 requires the commission to review the program before Oct. 31, 2027, with public comment. When will that review open, and how can residents comment?
Your state legislators
Should private plants serving one campus have to report their fuel, emissions and output publicly, the way utilities do?
Utah Office of Energy Development
Which of the companies at your public nuclear events are also partners on state-supported projects?
Rocky Mountain Power
How many large-load requests under S.B. 132 has the utility received, and how many went to private generators?
Your county commission
Are data centers a permitted use anywhere in our county, and do they need a public hearing?
Updates since this was posted
Tooele County, Oct. 7, 2026: the planning commission voted unanimously to table Chapter 34, the county's draft data center ordinance, until it can define what a data center is. The assistant county manager said the county will not accept a data center application until Chapter 34 is complete. Next meeting: Oct. 28. (KSL, Oct. 8, 2026)
Box Elder County, Oct. 15, 2026: Stratos filed a water rights change application. It lists 11 data center clusters, a 7.5-gigawatt power facility in fifteen 500-megawatt blocks, and 4,850 employees. The filing's own report calls the plant reciprocating engines; the news report described combined-cycle gas. A two-week notice and 20-day protest period follow. (Deseret News, Oct. 16, 2026)
Box Elder County: the county's 180-day data center moratorium, Ordinance 654, was adopted after it consented to Stratos and cannot reach the project; the draft development agreement excludes the project area from any moratorium. (Eight Project Areas)
Carbon County: Valar's Carbon plan is called "Project Beehive." Canary Media reported Oct. 14 that residents criticized the county's nondisclosure agreements. The county's July 3 statement defends them, saying some companies would not look at the county without them. (Canary Media, Oct. 14, 2026; Salt Lake Tribune, Sept. 24, 2026)
Inland Port Authority, Oct. 21, 2026: Executive Director Ben Hart told a legislative committee UIPA is not actively recruiting data centers, and that some data centers use its infrastructure. (UIPA hearing fact-check)
Trust Lands Administration Board, Aug. 20, 2026 transcript — utah.gov/pmn (partial read; see the nuclear page).
The Hive's Tooele Valley, Meta gas plant, Stratos and EDCUtah case files, linked above.